Commuters navigating one of north-east Delhi's worst traffic bottlenecks face a further three-month wait for relief, as the completion of the national capital's first double-decker flyover has been deferred to March 2027.

The 1.40-km integrated corridor between Yamuna Vihar and Bhajanpura was scheduled for completion by December this year. However, stringent construction restrictions imposed under the Graded Response Action Plan (GRAP) to combat deteriorating air quality across Delhi-NCR have brought civil works to a standstill, forcing yet another extension for the Rs 291.10-crore project.

Metro runs above, road still unfinished below

Designed as an architectural first for the capital, the double-decker structure carries an elevated Metro viaduct on its upper deck and a four-lane carriageway beneath it. Metro services began running on the upper tier on March 8, 2026, as part of the Pink Line's Majlis Park-Maujpur corridor, but motorists are still waiting for congestion relief because road surfacing is incomplete and the approach ramps on either side are unfinished.

Reports in July and October put the project at about 88 per cent complete, with the remaining work centred on the ramps and the road deck. The corridor is one of three double-decker viaducts being built by the Delhi Metro Rail Corporation (DMRC) under its Phase IV expansion, and the first of the three to near completion.

A history of missed deadlines

Announced in 2019 at an initial outlay of Rs 220.10 crore, the project estimate was later revised upward to Rs 291.10 crore. It was originally scheduled for commissioning by December 30, 2024, and its deadline was successively pushed to July and October 2025, then to December 2026, before the latest deferral to March 2027.

For nearly two years, progress remained stalled because statutory clearances for tree felling and transplantation along the alignment were delayed. The clearances finally came through in late 2024, and the DMRC began building the access ramps with the Public Works Department in March-April this year.

The DMRC is executing the project under an agreement signed with the Public Works Department in February 2021.

MLA promises earliest completion

Addressing concerns over the recurring delays, Ghonda MLA Ajay Mahawar said concerted efforts were being made to ensure the flyover was commissioned at the earliest, with continuous coordination maintained with the executing authorities and departments to accelerate the remaining works once environmental restrictions are lifted.

"Development works like these are important for public and our government takes their time-bound completion seriously. At the same time, we must ensure strict compliance with environmental norms in a city like Delhi, including by government departments. Hopefully, we will complete this project on time," Mahawar told The Tribune.

Until the lower deck opens, the corridor's road users will continue to rely on the congested surface roads of Bhajanpura and Yamuna Vihar, while Metro passengers above already use the completed upper tier.