Mumbai: The Union Ministry of Environment, Forest and Climate Change has directed a probe into Adani Green's 1,500 MW Tarali pumped storage project in Satara district, Maharashtra, after an Indian Express investigation reported that the project's declared cost was cut by 99 percent. The report, published on the newspaper's front page on Friday, says the cost was revised from Rs 5,675 crore to Rs 56.75 crore, or one-hundredth of the original figure.
According to the investigation, the revision also reduced the wildlife conservation deposit linked to the project. That deposit fell from Rs 227 crore to Rs 2.27 crore, the report says, a cut of the same proportion as the project cost itself.
The company has deposited Rs 56.75 lakh, described as one percent of the revised cost, into the account of the Sahyadri Tiger Reserve, according to the investigation. The project site falls within the landscape of the tiger reserve, which is why the wildlife deposit applies.
The matter reached the ministry through a complaint filed on 30 October by Rohan Bhate, the Honorary Wildlife Warden of Satara. Following the complaint, the ministry directed a probe on 6 November, the Indian Express reported.
Congress calls it a scandal of gigantic proportions
The Congress party has seized on the report. Senior Congress leader Jairam Ramesh described the episode as a "scandal of gigantic proportions" and demanded a probe by a Joint Parliamentary Committee, according to the Economic Times.
The Congress allegation is that the cost revision was designed to shrink the company's financial obligations towards wildlife conservation. The party has framed the issue as a question of both environmental accountability and corporate governance, and has pressed for a parliamentary inquiry rather than a departmental probe alone.
The allegations reported in the investigation and raised by the Congress have not been established as fact. The probe ordered by the ministry will examine the circumstances of the cost revision and the deposit.
What the probe will examine
Pumped storage projects store energy by moving water between two reservoirs at different heights, and they are a growing part of India's plan to balance renewable power on the grid. The Tarali project, at 1,500 MW, is a large installation of this kind.
The questions at the centre of the probe are why the project cost was revised so sharply, and whether the wildlife conservation deposit was recalculated correctly. The deposit is meant to fund conservation work in the affected landscape, and its size is linked to the project's declared cost.
The ministry's direction of a probe on 6 November came a week after the complaint was filed. The outcome of that inquiry will determine whether any further action follows, and whether the deposit is reassessed.